The Competition Appeal Tribunal approved a £260 million collective settlement between Professor Barry Rodger and seven Alphabet and Google entities on 16 September 2026, closing a claim brought on behalf of UK app developers twelve days before a ten-week trial was due to open in London. Of that sum, £160 million is set aside for eligible developers and £100 million for the funder, the after-the-event insurers and the legal team. Google admits no liability, and the tribunal will make no finding on whether the commission at the centre of the case was excessive or unfair.
In Short
A UK court has signed off on a deal under which Google pays £260 million to settle a claim that it overcharged app makers commission on the Play Store. If you ran a UK-based business that sold an app or in-app content through Google Play from August 2018 onwards, you are probably inside the class and entitled to a share of £160 million. Claims are not open yet: the administrator expects the four-month claim window to start six to ten weeks after approval, and no money moves until the tribunal signs off a second time.
What the tribunal approved
The order was made under rule 94 of the Competition Appeal Tribunal Rules 2015 in case 1673/7/7/24. Rodger and Google filed a joint application for a collective settlement approval order, signed on 25 August 2026 by David Gallagher, a partner at Geradin Partners, for the class representative, and by David Cran, a partner at RPC, for Google. The application asked the tribunal to find the terms just and reasonable within the meaning of section 49A of the Competition Act 1998.
Sequence matters here. The tribunal had listed the settlement hearing for 15 September 2026 with a time estimate of one day and one day in reserve, as PPC Land reported when the directions order was published on 26 August. Argument ran on the Tuesday and the order followed on the Wednesday. The settlement won approval from the Competition Appeal Tribunal on Wednesday, ending a collective action over allegedly excessive commissions. The claim website carries a one-line update recording that the tribunal "approved Professor Rodger's settlement on 16 September 2026."
The underlying settlement agreement was executed on 22 August 2026. Recital C of that agreement records that Google denies the conduct alleged and "believes it has strong defences" to the claim. Clause 10 states that entering into the agreement is not an admission of liability or wrongdoing by any party, and that neither the agreement nor any supporting document may be relied on as evidence of the truth of any allegation.
It is the largest settlement payout the tribunal has approved to date. Rodger was represented at the hearing by Robert O'Donoghue KC of Brick Court Chambers, Anneliese Blackwood of Monckton Chambers and Bethanie Chambers of XXIV Old Buildings, instructed by Geradin Partners.
Two pots, and the arithmetic behind them
The settlement agreement defines the Settlement Sum as two hundred and sixty million pounds, payable by way of compensatory damages and inclusive of interest and of all the parties' fees, costs and expenses, whether already incurred or still to be incurred in notifying class members and distributing the money. Google must pay it into a payment account within fifty days of the order.
The class representative divided that sum himself. £160 million forms the Class Pot for distribution to represented persons. £100 million forms the Stakeholder Pot covering the contractual entitlements of the funder, the after-the-event insurers, the solicitors and counsel. According to the settlement application, the Class Pot guarantees that 68.9 percent of the Settlement Sum, net of costs incurred, is available to represented persons.
The money will not sit with Google or with the law firm. Angeion Group, appointed by Rodger to administer claims and payments, will hold it in a segregated interest-bearing escrow account through AGI Trust Corporation, on trust, pending completion of the claims process and a further order. Interest earned while the sum is held is to be apportioned proportionately between the principal amounts eventually approved for represented persons and for stakeholders, subject to Google's submissions and the tribunal's directions.
One clause gives the structure a conditional edge. Clause 1.3 of the settlement agreement provides that if any of five named developers, the largest five by claim value, opt out of the proceedings under rule 82 or out of the settlement under rule 94, the Settlement Sum is reduced by the sums that would otherwise have been due to them, with repayment to RPC's client account within fourteen days of the end of the claim period. Clause 1.4 bars either side from encouraging those developers to leave. The settlement application records that at the time of filing, no indication of any such opt-out had been received.
The £7,500 line and the £200 floor
The distribution methodology, prepared by the economic consultancy Fideres and set out in Angeion's plan, splits the class in two at a revenue threshold.
Developers with estimated revenue of £7,500 or less across the Relevant Period may elect a fixed lump sum of £200, irrespective of their individually calculated damages. The plan describes this as a way of encouraging participation and reducing the administrative burden of calculating small losses one by one. Those developers retain the option of an individual calculation if they prefer it.
Developers above £7,500 receive an individual calculation. Each developer's assessed damages are divided by an aggregate damages figure to produce a percentage share of the Class Pot. A developer whose assessed damages represent one percent of the aggregate would receive approximately one percent of the pot.
The aggregate figure itself is an extrapolation. The transaction data Google disclosed to Rodger under paragraph 4.5 of a tribunal order made on 4 August 2025 runs only to the first quarter of 2025. Fideres projects forward from that cut-off to 31 July 2026 using each developer's observed share of transactions in the covered period, so that no developer has to supply fresh transaction records for the gap. The methodology rests on Professor Fletcher's preferred pooled counterfactual commission rate from her third expert report. It makes no separate adjustment for pass-on, simple interest or additional damages from off-app-store transactions. Where a developer's effective commission rate fell below that counterfactual rate, damages for the relevant transaction or period are treated as zero rather than negative.
Angeion is careful about the boundary of its own role. Its plan states that the firm "has not independently developed or validated the economic methodology" or the underlying damages calculations, except so far as needed to assess whether they can be implemented administratively.
A separate condition attaches at the top of the class. Clause 4.3 of the settlement agreement makes it a condition of distribution that each of the twenty-four developers listed in Annex A, the largest by claim value, represents and warrants that it is entitled to pursue the claims in the relevant transactions and that its related parties will not bring claims of their own over the same transactions.
The stakeholder pot is smaller than the bill
The £100 million does not cover what the stakeholders are contractually owed, and the application says so in terms.
As at 31 July 2026, the aggregate amounts claimed for stakeholder contractual entitlements and distribution costs totalled approximately £115 million, exceeding the pot by roughly £15 million, or 15 percent. Projected to the end of the distribution process, assuming the full remaining litigation budget is drawn, those entitlements and costs were estimated at approximately £134 million. That leaves a shortfall of about £34 million.
Bench Walk Guernsey PCC Limited, contracting on behalf of the GPS UK Funding Cell, agreed "not to insist on its contractual rights" where doing so would be likely to jeopardise approval of the settlement or leave the class representative unable to act in the best interests of the class, subject to consistency with the waterfall in the priorities deed.
The litigation funding agreement, originally dated 6 December 2023 and amended four times since, most recently by an agreement dated 20 July 2026, sets a Maximum Outlay of £27,671,000 and an initial tranche of £16,500,000. Its profit share is tiered by timing: £45,297,150.59 plus 400 percent of the capital outlay drawn from 1 June 2026 if proceeds arrive before the liability trial begins, rising to £81,894,301.17 plus 600 percent if they arrive afterwards. Settling before 28 September kept the claim in the lower tier. The agreement also caps the funder's total fee at the portion of proceeds the tribunal approves for it, and provides that the class representative must at all times "act fairly and adequately in the best interests" of class members.
The budget behind the Maximum Outlay is itemised by phase: £8,499,334.86 for the solicitor, £6,439,053.75 for counsel, £5,010,314.44 for economists, £3,323,254.45 in disbursements, £2,250,000 in after-the-event premium and £1,500,000 in indemnity, plus £649,042.50 of contingency. The single largest phase line is £9,557,000 for the trial of common issues, the phase the settlement removed. Rodger's own remuneration is set at £250 per hour plus VAT, capped at £40,000 in any twelve-month period.
Angeion's distribution costs are estimated at between £928,841 and £1,532,559 excluding VAT, with further costs from Fideres and Geradin Partners to be met from the existing litigation budget.
Payment order matters as much as amount. Stakeholders are not paid now. The application states that payments to them take place after the claim period has concluded and the sums due to represented persons are known, so that the tribunal can see how successful the uptake has been before releasing money to the funder, the insurers and the lawyers. Rodger described the completion and reconciliation of the claims process before any final distribution as an "important safeguard".
What happens next, and when
Angeion's timetable is a sequence of estimates rather than fixed dates.
Work before the claim period opens includes executing payment provider arrangements, deduplicating developer IDs, identifying multiple-account and succession cases, calculating provisional awards, producing the notice population, configuring the claim portal and verification workflow, and completing security and user-acceptance testing. That preparation is expected to take six to ten weeks from approval.
The claim period then runs for four months. For developers already matched to transactions in the disclosed data, the exercise is designed as a confirmation and payment election rather than a conventional claim. Each receives an individual notice stating that the developer has been identified as eligible, listing the relevant developer IDs, and indicating either the £200 fixed award or a provisional individual calculation. The developer then authenticates through a secure portal, confirms the developer IDs and the legal owner or successor entity, accepts or queries the figure, enters bank details and certifies that the submitter is authorised to receive payment. Supporting evidence is required only where a developer cannot be matched to the data, disputes the calculation, or raises ownership, succession or fraud questions.
Verification splits into three questions: entitlement, meaning whether the developer ID and transaction data place the developer in the class; authority, meaning whether the person completing the process may act for the legal owner; and payment destination, meaning whether the nominated account is appropriate. Low-value fixed payments get streamlined checks. Higher-value or disputed claims may require manual review, bank account validation and escalation to Rodger's legal advisers.
Notice runs primarily by email. Google will provide developer email addresses for the developers in the transaction data covering 22 August 2018 to 22 August 2024, where available and where it can share them consistently with its legal and regulatory obligations. The programme also includes reminders during the claim period, postal and telephone fallback, a website with FAQs and anti-fraud guidance, an email support line, a chatbot and a telephone line, and paid search, social and programmatic advertising. Enhanced outreach, meaning additional follow-ups by email, telephone and post, is proposed for developers with an award value of £20,000 or more, mirroring the $20,000 threshold used in the United States comparator.
After the claim period closes, Angeion expects claim review to take approximately 30 to 60 days, initial payments to issue within a further four to six weeks, and a further six to eight weeks to handle returned payments, corrected details and reissues. Where payments go by Bacs, the standard cycle is three business days. No payments will be made until a further order of the tribunal, and the class representative must return for approval of the final distribution and the stakeholder payments.
Represented persons who do not want the settlement have a route out. The draft order requires a UK-domiciled represented person to opt out no later than three months after the date of publication of the settlement notice. The claim website states that the deadline and the mechanics will be published in the settlement notice in due course.
Take-up is the number that decides the outcome
Because the Class Pot is fixed and the stakeholder shortfall is real, participation rates determine both how much reaches developers and what is left over.
Angeion plans on approximately 50 to 80 percent take-up by value and approximately 8 to 15 percent by number. The value range reflects the concentration of claim value among a small group of large developers, and the fact that Geradin Partners has already had direct engagement with developers representing roughly 80 percent of the total claim value. The firm's legal advisers were in direct contact with sixteen developers at the time of filing.
The comparators are American. In Cameron v Apple, a US$100 million settlement covering 67,440 eligible iOS developer accounts, uptake reached 13.21 percent of accounts and 32.10 percent of the sum available to the class, with participation rising materially alongside developer revenue, from 9 to 28 percent in lower tiers to 30 to 36 percent in higher ones. Once developers engaged, completion was near total: by January 2025, 8,658 of 8,935 payments had been made, 97 percent by number and 99 percent by value. In re Google Play Developer Antitrust Litigation settled for US$90 million across 47,972 eligible developer accounts.
Angeion flags the principal difference. Both American settlements were confined to smaller developers, with Cameron applying a US$1 million annual App Store proceeds threshold and the US Google Play case a US$2 million threshold. The UK class has no such cap, and Cameron's highest payment tiers produced estimated individual recoveries of approximately US$41,000, US$82,000 and US$124,000, well below what the largest UK developers stand to receive. On that reading, Cameron's take-up by value is a conservative benchmark rather than a ceiling.
Whatever remains undistributed goes back before the tribunal at a second hearing. Rodger's present proposal is that residual damages first meet stakeholder entitlements not covered by the Stakeholder Pot, then top up validly claiming developers pro rata. Google has reserved the right to make its own submissions on that question.
The trial that did not happen
The settlement arrived at the end of a hard-fought year, and the application sets out what the class was giving up and what it was avoiding.
The trial was listed for ten weeks from 28 September 2026, running jointly with the consumer claim brought by Helen Elizabeth Coll in case 1408/7/7/21. Rodger's skeleton argument was due on 11 September. A first-instance judgment would have been unlikely before summer 2027, and any appeal could have added a further twelve to twenty-four months. A possible Second Hearing on intra-group arrangements, directed at the pre-trial review, raised the prospect of another round of factual and expert evidence and another avenue of appeal.
The cost exposure was concrete. Rodger was budgeted to incur approximately £3.35 million in additional costs through trial, with appeal costs estimated to exceed £750,000 and a Second Hearing roughly costed at over £1 million, none of which the existing funding arrangements covered. Compliance with disclosure orders, whose deadline the tribunal extended to 2 October 2026, could have added more than £1 million on its own. Four developers had applied to opt out after Google's disclosure applications, generating further unbudgeted work.
Google's own procedural campaign shaped the endgame. The company applied on 27 February 2026 to vary the collective proceedings order so the twenty-five largest developers by claim value would proceed on an opt-in basis. The tribunal dismissed that application on 4 June 2026 while holding that Google could seek disclosure from individual represented persons under rule 89(1)(c). Google issued seventeen disclosure applications on 12 June. Hodge Malek KC granted a narrowed application against one developer following a hearing on 9 July, and granted the outstanding applications against ten other developers on 7 August. DAZN Group Limited was permitted to opt out of the proceedings outside the normal window by an order drawn on 19 June 2026.
The application also points at the Apple precedent as a warning about timing. In Kent v Apple, trial began on 13 January 2025 and produced a judgment for the class in late October 2025. More than ten months after judgment, and nineteen months after the trial opened, the class had received nothing, with payment contingent on Apple's appeal, listed over five days in May 2027.
Google's substantive position is unchanged by the settlement. The company maintains it is not dominant on any properly defined market, and its expert Robin Noble identifies a market for the facilitation of digital content transactions in which Google Play faces competition from other distribution channels. Rodger did not commission a separate independent legal opinion for the approval application, citing cost to class members and the support he had already received from his consultative panel and Nicholas Bacon KC, an approach consistent with Merricks v Mastercard, where the tribunal confirmed "there is no requirement for there to be an independent opinion".
Why it matters for marketers and app businesses
For anyone monetising through Google Play, this remains a compensation event rather than a structural one. Nothing in the approved settlement changes commission rates, billing rules or distribution terms, and the tribunal made no finding on whether those terms breached competition law.
The commercial terms moved on their own track and faster. Google separated its Play service fee from its billing fee on 24 June 2026, producing a restructured card that PPC Land reported at 25 percent for the combined charge, with the new structure taking effect for transactions with users in the EEA, the United Kingdom and the United States from 30 June 2026. In the EEA the pressure came from a different direction: the European Commission fined Google 890 million euros on 23 July 2026, of which 430 million concerned restrictions on Play developers steering users to alternative purchase channels under the Digital Markets Act, and Google publicly rejected the findings in the same week. Earlier, Google had rolled out user choice billing to UK app developers on 29 March 2025 with a four percentage point discount off the standard service fee, following engagement with the Competition and Markets Authority.
The regulatory backdrop has not softened. The Court of Justice dismissed Google's appeal against the 4.125 billion euro Android fine on 2 July 2026. The CMA had designated Google with Strategic Market Status on 30 September 2025, then in February 2026 accepted voluntary commitments from Apple and Google on app review transparency rather than imposing binding conduct rules. In the United States, an injunction requiring Google to open the Android app storefollowed Epic's jury verdict in October 2024, and Google and Epic filed a modified injunction in November 2025 that preceded Epic's withdrawal from the London case on 9 March 2026.
The contrast with Apple is the sharpest read on what a settlement costs a class in precedent. The Competition Appeal Tribunal ruled on 23 October 2025 that Apple had abused its dominant position in app markets, finding its commissions excessive and unfair. That claim produced a judgment. The Rodger claim produced money, sooner, with no finding attached.
For advertisers watching the same regime from the buy side, the procedural signal travels. On 5 August 2026 the tribunal certified an opt-out claim valued at around £5 billion on behalf of UK businesses that bought Google search ads between 2011 and 2025. That class is at the beginning of the road the developer class has just left, and the disclosure rulings of July and August 2026, along with the tribunal's warning about applications that push class members toward opting out, form part of the map.
The consumer side of the Play Store dispute has not settled. Coll's separate claim, alleging that around 20 million UK consumers paid more than they should have on Google Play, is due to proceed to trial on 5 October 2026, covering purchases made between 1 October 2015 and 31 July 2026. Google contests the allegations.
Timeline
- 22 August 2018: Start of the relevant period for the developer class
- 6 December 2023: Rodger's litigation funding agreement with Bench Walk executed
- 7 October 2024: A United States federal judge orders Google to open the Android app store to third-party access
- 23 August 2024: Rodger files the collective proceedings claim form, case 1673/7/7/24
- 20 December 2024: First case management conference in the Rodger proceedings
- 6 March 2025: Certification hearing before the Competition Appeal Tribunal
- 12 March 2025: First amendment to the litigation funding agreement
- 14 March 2025: Joint case management decision on the Rodger, Coll and Epic claims
- 24 March 2025: Tribunal orders joint case management of the three sets of proceedings
- 29 March 2025: Google rolls out user choice billing to UK app developers
- 23 May 2025: Collective proceedings order made, certifying the claim on an opt-out basis
- 4 August 2025: Tribunal orders disclosure of the Google transaction data underpinning the distribution methodology
- 23 August 2025: Opt-out deadline, 4pm, for the original class cohort
- 30 September 2025: The CMA designates Google with Strategic Market Status
- 23 October 2025: The tribunal rules that Apple abused its dominant position in app markets
- 4 November 2025: Google and Epic file a proposed modified injunction in the United States
- 15 and 17 December 2025: Further amendments to the litigation funding agreement
- February 2026: The CMA accepts voluntary app store commitments from Apple and Google
- 27 February 2026: Google applies to vary the collective proceedings order so the 25 largest developers proceed on an opt-in basis
- 9 March 2026: The Epic proceedings are withdrawn following a separate settlement
- 4 June 2026: The tribunal dismisses Google's variation application
- 12 June 2026: Google issues 17 disclosure applications against larger developers
- 19 June 2026: DAZN Group Limited is permitted to opt out of the proceedings
- 24 June 2026: Google Play splits its service fee from its billing fee
- 2 July 2026: The Court of Justice dismisses Google's appeal against the 4.125 billion euro Android fine
- 9 July 2026: Hodge Malek KC grants a narrowed disclosure application against one developer
- 13 July 2026: Date of Google's second disclosure application
- 20 July 2026: Amendment agreement restating the litigation funding agreement
- 23 July 2026: The European Commission fines Google 890 million euros, including 430 million over Play steering restrictions
- 31 July 2026: Pre-trial review; the tribunal amends the collective proceedings order and extends the relevant period to this date
- 3 August 2026: Rodger accepts Google's £260 million offer in principle after consulting his consultative panel
- 5 August 2026: The tribunal certifies a separate opt-out claim of around £5 billion on behalf of UK advertisers
- 7 August 2026: Hodge Malek KC grants the outstanding disclosure applications against ten further developers
- 22 August 2026: Settlement agreement executed
- 25 August 2026: Joint application for a collective settlement approval order signed and filed
- 26 August 2026: The tribunal publishes its directions order for the settlement hearing
- 10 September 2026: Deadline, 4pm, for represented persons to file written submissions
- 11 September 2026: Date on which the class representative's trial skeleton argument was due
- 15 September 2026: Settlement approval hearing opens
- 16 September 2026: The Competition Appeal Tribunal approves the £260 million settlement
- 28 September 2026: Date on which the joint ten-week trial had been listed to commence
- 2 October 2026: Extended deadline for represented persons to comply with the disclosure orders
- 5 October 2026: Trial date for the parallel consumer claim brought by Helen Elizabeth Coll
Related PPC Land coverage
- Google's £260m app developer deal faces tribunal hearing on 15 September - The tribunal file behind the proposed settlement, including the certification numbers, the funding structure and the disclosure fight that preceded it.
- Google faces £5bn UK advertiser claim as tribunal certifies opt-out case - A separate opt-out claim certified on 5 August 2026 covering UK businesses that bought Google search ads between 2011 and 2025.
- UK tribunal rules Apple abused dominant position in app markets - The October 2025 judgment that took a comparable app store commission claim to a finding of abuse rather than a settlement.
- Google Play developers face 25 percent fee under new structure - The June 2026 separation of service fee from billing fee, which reset the commission arithmetic the claim was built on.
- Google launches user choice billing for UK app developers - The March 2025 UK rollout of alternative billing with a four percentage point service fee discount.
- UK watchdog lets Apple and Google write their own rulebook - The CMA's February 2026 acceptance of non-binding app review commitments instead of conduct requirements.
- CMA designates Google with Strategic Market Status following investigation - The first designation under the Digital Markets, Competition and Consumers Act 2024, made on 30 September 2025.
- EU fines Google 890 million euros and gives it 60 days to fix search - The July 2026 non-compliance decisions, including 430 million euros over Play Store steering restrictions.
- Google weighs appeal, says 890 million euro EU fine kills Search - Google's public response to those decisions.
- Google loses 4.1 billion Android fine as EU court dismisses appeal - The Court of Justice confirming the Android tying and anti-fragmentation findings on 2 July 2026.
- Google and Epic propose Android settlement modifying antitrust injunction - The November 2025 United States settlement that preceded Epic's withdrawal from the London proceedings.
- Google ordered to open Android App Store in antitrust ruling - The October 2024 United States injunction that followed Epic's jury verdict.
- Google's app store monopoly faces setback as court denies stay request - The September 2025 refusal of a stay, and the compliance changes it set running.
- Indonesia imposes $12.4 million fine on Google over Play Store billing practices - The January 2025 Indonesian decision on mandatory Play billing, an earlier instance of the same conduct drawing a penalty.
- Google settles US Play Store anti-trust lawsuit - The December 2023 settlement with state attorneys general over Play Store payment and distribution rules.
Summary
Who. Professor Barry Rodger, a competition law academic at the University of Strathclyde and the certified class representative for UK-domiciled third-party app developers, and seven defendants: Alphabet Inc, Google LLC, Google Ireland Limited, Google Asia Pacific Pte Limited, Google Commerce Limited, Google Payment Limited and Google UK Limited. Geradin Partners acts for the class representative, RPC for Google, Bench Walk Guernsey PCC Limited funds the claim, Angeion Group administers claims and payments, and Fideres calculates entitlements.
What. Approval of a collective settlement worth £260 million, split into a £160 million Class Pot for developers and a £100 million Stakeholder Pot for the funder, insurers, solicitors and counsel. Developers with £7,500 or less in qualifying revenue may take a fixed £200; larger developers receive a share of the Class Pot proportionate to their assessed damages. Google makes no admission of liability, and stakeholder entitlements already exceed their pot by about £15 million, projected to reach a shortfall of roughly £34 million.
When. The claim was filed on 23 August 2024 and certified on 23 May 2025. The settlement agreement was executed on 22 August 2026 and the joint approval application filed on 25 August. The hearing opened on 15 September 2026 and the tribunal made its order on 16 September. Google must pay within fifty days. The four-month claim period is expected to open six to ten weeks after approval, with claim review taking a further 30 to 60 days and initial payments four to six weeks after that.
Where. The Competition Appeal Tribunal in London, case 1673/7/7/24. The class covers UK-domiciled third-party app developers that made a qualifying sale through Google Play between 22 August 2018 and 31 July 2026.
Why. The claim alleged that Google excluded rival Android distribution channels and charged commissions of up to 30 percent that were excessive and unfair. Settling twelve days before a ten-week trial removed the risk of a judgment delayed into 2028 by appeal, avoided several million pounds of unbudgeted cost, and kept the funder's return in the lower of two contractual tiers. It also ends the case without any finding on the merits, leaving the commission structure untouched and leaving the parallel consumer claim to be tried in October.
Discussion